Street Project Updates & Proposed Asphalt Paving Program Project List for 2018

0
720

City of Marshfield Board of Public Works Approves Preliminary 2018 Asphalt Paving List

The City of Marshfield Street Division has been busy this summer with various projects. A complete list was submitted to the Board of Public Works on October 16 (also listed below).

Watch the Full Meeting here:

Asphalt Mill-In-Place

  • Hawthorn Ave (cul-de-sac to cul-de-sac) – Pulverizing scheduled for the week of October 16th, paving to be scheduled
  • 8th St (Linden to Holly) – Pulverizing scheduled for the week of October 16th, paving to be scheduled 12th St (Central to Maple) – complete
  • Arnold (Hinman to cul-de-sac) – on-going, pulverizing is scheduled for the week of October 16th, paving to be scheduled
  • Carmen (Palmetto to Waushara) – pulverizing scheduled for the week of October 16th, paving to be scheduled
  • Kathrine Ct (cul-de-sac) – pulverizing scheduled for the week of October 16th, paving to be scheduled
  • Cherry Ave (Franklin to Grant) – complete
  • Forest St (Cherry to Plum) – complete
  • Plum Ave (Franklin to Grant) –complete
  • Hawthorn Ave (5th to Adler) – complete
  • Hume Ct – complete
  • Laird St (Adams to North Hills) – complete
  • E 4th St Shoulders (Hume to Anton) – complete Asphalt

Overlays

  • (Ives to Kalsched) – complete
  • Laurel St (Veteran’s to Wood) – scheduled to be paved on Saturday October 21st, 2017
  • Walnut Ave (Doege to Ives) – complete
  • Franklin (Central to Cedar) – on-going, only paving Central to Maple
  • Adams Ave (5th to Adler) – complete
  • 4th street, Adams to the east- complete
  • Cedar Avenue, Ives to the south match line- to be scheduled

Street Reconstructions

  • 21st St (E of Tamarack) – complete
  • Adler road, Adams to 750’ east- scheduled to start October 17th

Storm Sewer Maintenance/Construction

  • Catch basin repairs
  • Several culvert installations
  • Storm sewer installed on 12th street
  • Repair storm sewer on Martin Drive
  • Build end wall on storm sewer at Wallonnie Drive
  • Storm sewer installed on Carmen Drive/Katherine Ct.
  • Storm sewer installed at 8th street and Linden Avenue

Sanitary Sewer Maintenance/Reconstruction

  • Replace sanitary manhole on Laurel/Laurel Ct. and remove unnecessary sanitary manhole

Street Maintenance

  • Sweep roads- on going
  • Patch roads- on going
  • Blade roads and Alleys
  • Mow city owned land
  • Pick up dead deer
  • Mow city owned property
  • Weed control
  • Treat Ash trees- complete

Contracted Services

  • Crack filling- regular crack filling has been completed
  • Mowing city owned property- on going
  • Slag seal- complete Mono form manholes from approved list- 10 manholes completed
  • Epoxy painting complete

Preliminary 2018 Asphalt Paving List

As of now, the proposed list is 4.7% below the budgeted amount, but staff are estimating on cost at this point. Learn more about city street repairs here. The total estimated cost is $1,864,138. Also preliminary is the actual list itself, which is subject to change.

“We call it preliminary, because it could change,” said Dan Knoeck, Public Works Director.

Streets proposed for OVERLAY include:

  • Columbus Drive (5th to Adler)
  • Blodgett St (Willow to Peach)
  • Upham St (Chestnut to Oak)

Street proposed for MILL-IN-PLACE include:

  • 18th Street (Pecan to Washington)
  • Balboa Ave (17th to Cul-de-sac)
  • 21st St (Maple to Vine)
  • Colonial St (Adams to North Hills)
  • Palmetto Ave (Depot to Blodgett)
  • Wallonnie Dr (Palmetto to Palmetto)
  • Auburn Ave (Blodgett to Fillmore)
  • Ridge Rd (Schmit to Cul-de-sac)

 